Traffic Alert: Gas Pipeline Project around Emory

From Emory:  This month Atlanta Gas Light began a pipeline replacement project---a non-Emory project that will produce one-lane closures in the Emory area including Clifton, Houston Mill and North Decatur roads––that will last through August.

 

Replacement work will occur during daytime and evening hours and, where possible, AGL will install the pipe outside of the roadway along the public right-of-way. Any work requiring a lane closure will follow DeKalb County traffic control guidelines with signage, cones and flaggers to assist traffic flow. AGL  is coordinating with the Emory to minimize inconveniences to commuters and to avoid work during Commencement activities. Cliff shuttle routes will not be impacted by this project (http://emory.transloc.com/)

AGL project map:   www.aglc.com/prp.  Questions:  AGL  (404) 584-3039 or pipelinereplacements@aglresources.com.

 

Current work schedule:

 

Area of Work

Anticipated Start

Anticipated Duration

Lane Closure

Daily Schedule

N.Decatur Road (Scott Blvd to Clairmont Ave)

Underway (January)

10-12 working weeks

Westbound lane

Mon – Fri

9:00 a.m. – 4:00 p.m.

Clifton Road (Michael Street to Houston Mill Road)

Week of February 13

4-5 working weeks

Northbound lane

Sun – Thurs

7:00 p.m. – 5:00 a.m.

Clifton Road (Houston Mill Road to Clifton Way)

Week of March 8

3-4 working weeks

Northbound lane

Sun – Thurs

7:00 p.m. – 5:00 a.m.

Houston Mill Road (Clifton Road to Gatewood Road)

Week of April 1

1-2 working weeks

Northbound lane

Sun – Thurs

7:00 p.m. – 5:00 a.m.

Houston Mill Road (Gatewood Road to Logans Knoll)

Week of April 16

5-6 working weeks

Northbound lane

Mon – Fri

9:00 a.m. – 4:00 p.m.

Houston Mill Road (Mason Mill Road to Lavista Road)

Week of May 21

10-12 working weeks

Northbound lane

Mon – Fri

9:00 a.m. – 4:00 p.m.

N.Decatur Road (Clairmont Avenue to Haygood Drive)

Week of May 28

10-12 working weeks

Westbound lane

Mon – Fri

9:00 a.m. – 4:00 p.m.

 

Groups: